Project Scope of Work

Ronkonkoma Middle School

 

  • Asphalt Pavement and storm drainage
    The existing bus loop is prone to flooding during heavy rain events. Additional storm drainage structures will be installed and asphalt will be repaired. 

  • Auditorium reconstruction
    The request was made to make renovations to the existing Auditorium. The list of improvements include as follows; replace all house lighting with LED and tie into new lighting board, new ceiling hung projector, replacement of existing sound system and board, acoustically treat the rear walls of the space, properly run new wiring to sound board using a combination of saw cutting floor and furring out half wall adjacent to the folding partition. Provide A/C into the auditorium. Provide separate controls to each section when dividing walls have been extended. 


  • Vinyl Asbestos Floor Tile Abatement
    Replace all remaining asbestos floor tile and vinyl cove base. Bulk scrape all existing mastic. Furnish and install new vinyl composite tile, 6" rubber cove base. Proper floor prep prior to installing new flooring shall also be required. Work shall be completed in strict accordance with NYSDOL ICR 56.


  • HVAC Reconstruction
    As part of the 2014 capital projects, the district under a partial DW unit ventilator replacement. To date there are still 35 original UV's located within the building and the request was made to replace these units. The recently installed controls can be removed and reinstalled onto the new units as part of this project. Install mechanical fresh air ventilation to (2) locations within existing building. Additionally, the cost to convert all existing equipment from pneumatic to DDC is included as well. This will include, fan coil units, convectors, ceiling hung H&V units and appx. 55 exhaust fans.

  • Refurbishment of Library to create Media Center
    Convert existing library into a multi functional media center intended to expand students creativity where they can gain access to information and resources. The term used Is a "shared learning space". This will involve new furniture including flexible seating options, and shelving, ceiling and lighting replacement, replacement of existing flooring, electrical, demolition, technology a new circulation desk, finishes and carpentry. Open wall between the existing library and the computer lab with a glass partition which will improve line of site and allow for the spaces to feel larger than they are. Creation of flexible teaching spaces will also be incorporated into the project.

  • Freight Elevator Installation 
    Replace existing freight elevator and control.   We recommend the installation of a new freight elevator including replacement of electrical wiring and freight doors. Existing shaft shall be reused.

  • Steam piping replacement and asbestos abatement
    Remove all existing asbestos pipe wrap from all existing crawl space and perimeter sand tunnels. Replace all existing supply and return lines as well as cast iron sanitary lines. Reinsulate all newly installed supply and return piping.

  • Replace Existing underground Electric Service
    Replace existing incoming Primary lines from street to existing pad mounted transformer.